Background – A Chlorine Scrubbing column was installed on a system that extracted fumes from a reactor. The level of Chlorine in the discharge from the scrubber exceeded the prescribed limits so I was tasked with designing a new scrubber to operate in series with the existing scrubber.
This project involved
Pondering plant issues at William Blythe
Existing Chlorine Scrubber having its packing maintained.
This was the first job Euton saw through the whole project cycle from concept to operation, 4 to 5 years into his career. Subsequently he designed
Euton has also been involved in troubleshooting
New Cl2 Scrubber to the left of the existing one
Background –In 2001 the OSPAR committee recommended a 15% reduction of oil discharged in produced water based on the producer’s calendar year 2000 produced water discharges. In addition, it was recommended that the monthly average oil in water (OIW) concentration limit be reduced from 40 mg/l to 30 mg/l. In the UK the DTI arranged for these changes to be implemented in 2006 so that the industry could adjust for the new requirements. For one asset Euton was involved in, produced water rates had doubled in the years post 2000 which meant that the required OIW discharge concentration to meet the new requirement was 5 mg/l – a big ask for any abatement system.
Euton was tasked with carrying out a trial of Epcon Compact Flotation units on the installation. He designed the trial and captured a comprehensive set of results to enable a thorough review of the technology to be made by the client. After receiving the report the client gave him responsibility for the installations Produced Water projects.
He next carried out a comprehensive review of the existing produced water equipment – reviewing the separator design, hydrocyclone operation and optimisation, degasser performance and gas flotation sparge system.
Finally, he was tasked with designing a Produced Water Reinjection trial using hired diesel driven pumpsets to inject produced water into one of the platform’s seawater injection wells. Despite some issues with the pumpsets transmitting vibrations to the platform pipework we were able to successfully prove the concept.
Produced Water Workshop details
After PWRI was selected as the preferred option Euton carried out the conceptual design of a full scale PWRI system. This involved converting a train of the existing seawater injection booster and injection pumps for produced water injection. This approach saved procurement and delivery time for new pumps enabling implementation of the project 12 months earlier and in time for the OSPAR implementation deadline. Following detailed design and installation he commissioned the new PWRI system that was capable of injecting 60kbwpd of produced water.
He was asked to write a paper summarising this work after delivering a presentation to the DTI Produced Water group. Euton has also carried out
More recently he carried out a review of the produced water challenges of the Erskine production module on Lomond
Paper published at Produced Water Workshop 2007